Vertical all pipe lines completed
Plumbing Drainage Services work in progress
8th Passanger lift installed | 13th Passanger lift work in progress
Residential and fire staircase steps completed
West site tilling flooring, Toilet dado, kitchen platform completed upto 80%
Electrical work completed upto 80%
West side building view
Common passage lobby completed upto 8th floor
West side building view
West side paving block work completed
Residential lift installed & lift cladding completed 1st floor to 11th floor
East side 5th to 8th series flats' Aluminium windows fixed upto 11th floor
East side 5th to 8th series Flats' safety doors fixed upto 11th floor
East side 5th to 8th series Flats' Flush doors fixed upto 11th floor & door fittings completed upto 7th floor & work in progress
Refuse area IPS flooring completed
Flat no 301, 402, 403, 404 terrace waterproofing work in progress
Tilling work west side 1st to 4th series flats, work in progress 5th to 8th series flats completed upto 11th floor
Chemical waterproofing and plumbing services work on progress
East side 5th to 8th series Flat putty and 1st coat of OBD work in progress
Parking Tiles work in progress
Paving Block fixing work in Progress
Residential Meter room work in progress
Downtake line completed for series 5/6/7/8/1/2 & Duct primer completed for all ducts
8 passenger lift shaft ready for car erection
West side External Plastering Completed
Front side shop passage ceiling painting work in progress